Final Footer Prep
Crews worked today on getting the footer preped for wall erection tomorrow. The crane is scheduled to be on-site late this afternoon and be assembled early in the morning.

Footer marked for rebar kick dowel drilling.

A jobsite should never be without its safety can.

All measurements are double checked against an on-site set of plans.

Every panel is measured and marked.

Shims await their final positions in the next few days.

Rebar kick dowels are ready-to-go.

Wall panels are clean and ready.

These kick dowels are waiting to be inserted into the footer.

A worker drills the footer for kick dowel installation.