All interior walls, including this one in the conference room, will be well insulated.


The sound stage’s ceiling structure now has a fresh coat of black paint.


The roof structures and HVAC duct work is now flat black in the cafe too.


Two layers of 5/8-inch sheetrock now cover the interior walls of the screening room.


Insulation installation is almost complete throughout the entire facility.


The machine core is getting closer to being completely enclosed.


The audio suite too is almost finished with sheetrock.


The second layer of limestone awaits compaction.


The hallway past operations in the post-production wing.


The framework for the front and rear facades is now installed.

Reception area

Conceptual visualizations were completed today to begin the final preparations for millwork construction in the reception area.

Sheetrock, ceiling painting and more…


The freshly primed front facade and a new layer of limerock.


Painting of the exposed ceiling.


Specialty framing is nearing completion.


The screening room now has walls.

Sheetrock, Parking Lot, Electrical, Exterior Priming and the minor details

Work continues at a blistering pace as walls are now going up and the interior of the facility really begins to take shape.


Sheetrock is being installed quick time!


The exterior has been primed and is undergoing detailed patching.


Electrical connections are being made.


Backing and bracing along with other “behind the wall” details are being installed.


This is the hall between the graphics and sound design suites.


The view from inside the core… walls are closing in.


Surveyors determine grade levels for the parking lot.


The parking lot is nearing completion.


Sheetrock and mud awaits installation.

Parking lot, exterior priming and HVAC

Work continues at a steady pace with the limerock for the parking lot going in as well as primer on the exterior walls. Interior sheetrock is due to start as soon as the windows and doors get installed sometime the middle of next week.


The machine core in the post-production wing.


Painting the primer.


Ceiling mounted air handlers in the reception area.


One of the audio suites.


One of the large edit suites.


The cafe.


The studio.


The parking lot gets limerock.


Curbs and limerock in the parking lot.


More parking lot.


We have a transformer now!


Every pipe must get insulation.

Curbing and framing


Installation of the curbs from the road.


Portals for the critical reference monitors have been framed.


Blue skies and cool temperatures are a welcomed.

Sidewalk install begins and electrical and framing fixes


Pours for the sidewalks began this morning.


In-floor electrical needed to be re-routed a few feet… oops!


Changes in framing have been noted.

Framing & HVAC continues


The screening room now has walls.


Framing out around the windows in the front facade.


The shower is now installed.


Connecting the power at the street.


Wiring in the transformer.


The electrical panels… man those are big.


The hall from the production department into the cafe.

Framing, Electrical, HVAC continues


Insulation on the interior of the exterior walls is installed.


The new shower’s here!


Fuse boxes are now going into the panels.


Water from rains for the past 3 days have filled the parking lot.


Duct installation continues in the cafe.


The front parking lot full of water.


The vestibule to the restrooms and the copy room.


Concrete clean-up still continues.